Weald Of Kent Grammar School – Design and Build Sports Ball Hall

Weald Of Kent Grammar School – Design and Build Sports Ball Hall

10 month project A design and build construction project comprising a new detached sports hall (1300m2) with ancillary areas including provision of new changing rooms, fitness suite, viewing gallery, studios, coffee shop and kitchen and reception area complete with all services, new drainage provisions and external works and associated alterations…

SEE THE CASE STUDY

Berkely House Lynsted Faversham – Residential Care Home Facility

Berkely House Lynsted Faversham – Residential Care Home Facility

Project: Design and Build of 4 new residential care bungalows with adjacent staff accommodation Programme: 8 months Cost: approx. £600k Site Description: Berkeley House is made up of two separate dwellings within beautiful grounds located within the peaceful rural Kent countryside. The property back onto very large grounds in which…

SEE THE CASE STUDY

Radnor House School Sevenoaks

Radnor House School Sevenoaks

Site: Radnor House School Sevenoaks – (Formerly Combe Bank School, Sevenoaks) Project: Demolition of obsolete structures and window refurbishment to main front elevation Programme: 8 Weeks Cost: approx. £250k Site Description: Radnor House School Group is an independent school with sites in Sevenoaks and Twickenham. The Sevenoaks campus is extensive…

SEE THE CASE STUDY

Walthamstow Hall School New Ball Hall

Walthamstow Hall School New Ball Hall

Construction of new Ball Hall with studios, changing facilities and meeting rooms.

SEE THE CASE STUDY

St Marys

St Marys

St Marys RC Primary School Gillingham   Type of Project: Front Reception Extension Rough size sq m wise of project: 30m2 Duration of project: 4 months. Jul-14 – Nov-14 Removal of existing entrance porch, design and build of new front entrance including construction of new disabled toilet, new store, new…

SEE THE CASE STUDY

St James

St James

Project type: Classroom Extension Rough size sq m wise of project: 102m2 Duration of project: 5 months. Sep 2014 – Jan 2015 Approx contract value: £218,000 Demolition of mobile classroom and construction of new classroom with store and connecting corridor. External works include new access route, new paving and adaptations…

SEE THE CASE STUDY

St Michaels RC Primary School Chatham

St Michaels RC Primary School Chatham

Project type: Classroom Extension
Rough size sq m wise of project: 100m2
Duration of project: 5 months. Oct 2014 – Feb 2015
Approx contract value: £200,000

SEE THE CASE STUDY

Holy Trinity CE Primary School Dartford

Holy Trinity CE Primary School Dartford

Project type: New Classroom & toilets
Rough size sq m wise of project: 95m2
Duration of project: 5 months. Oct 2014 – Feb 2015
Approx contract value: £180,000

SEE THE CASE STUDY

Bishop Ridley CE Primary School Welling

Bishop Ridley CE Primary School Welling

Project type: Classroom Extension
Rough size sq m wise of project: 100m2
Duration of project: 5 months. Oct 2014 – Feb 2015
Approx contract value: £200,000

SEE THE CASE STUDY