Holy Trinity CE Primary School Dartford

  • Project type: New Classroom & toilets
  • Rough size sq m wise of project: 95m2
  • Duration of project: 5 months. Oct 2014 – Feb 2015
  • Approx contract value: £180,000

Construction of a single classroom and toilet accommodation to the side of the existing school. Works included adaptations to the existing flat roof over the corridors to ensure rainwater disposal.

Construction works included temporary works, adaptations, building services, landscaping and infrastructure works necessary.